Completed case study · Two-form-entry primary-school annexe
Plumcroft Primary School SFS and façade package
Vincent Road, Woolwich, London SE18 6RG, United Kingdom
Dmitro Facades was instructed by Frencon Construction to deliver the SFS and façade-envelope package at Plumcroft Primary School’s Vincent Road campus. The record identifies a £769,931 contract basis and later retention activity, while keeping whole-school completion context separate from the exact Dmitro package evidence. That boundary remains explicit throughout this record.
Service family
Systems & materials
- Client
- Royal Borough of Greenwich
- Architect
- Pollard Thomas Edwards
- Main contractor
- Frencon Construction Limited / Glenman group
- Delivery entity
- Dmitro Facades Ltd
- Sector
- Two-form-entry primary-school annexe, 2,750m2 GIFA, 420-place planning context, BREEAM Excellent
- System
- Metsec SFS, sheathing
Project context
Primary-school campus/annexe. Two-form-entry primary-school annexe; 2,750m2 GIFA; 420-place planning context; BREEAM Excellent
Dmitro scope
Dmitro Facades was instructed by Frencon Construction in May 2017 on a £769,931.92 SFS and facade-envelope package at Plumcroft Primary School’s Vincent Road campus; later retention records support real commercial delivery involvement.
Systems & materials
Materials and products included Metsec named. The evidenced assemblies include metsec sfs, sheathing, insulation, fire barriers, breather membrane, cladding and standing-seam roof.
Delivery & coordination
- SFS
- sheathing board
- insulation
- brick channels
- cladding
- fire barriers
Programme & evidence
Frencon LOI expressly instructs work; later retention and second-half-refund entries document commercial delivery involvement
- SFS
- sheathing board
- insulation
- brick channels
Outcome
Whole school completed and awarded externally; exact Dmitro PC date and full package completion not directly document
Commercial record
- subcontract/contract value
- £769,931.92 gross ex-VAT lump-sum order/contract basis
- retention
- 5% retention terms
- retention
- £1,562.68 retention bill 2018-04-18
- retention
- £330.25 second-half retention-refund invoice 2020-02-20
Related expertise
Related projects
All projectsroof system
50 Woodside Road
50 Woodside, Wimbledon, London SW19 7AE, United Kingdom
barriers system
New Pier Wharf, Odessa Street
1–3 Odessa Street, Rotherhithe, London SE16 5UH, United Kingdom
barriers system
Plaistow Hub
London Road, Plaistow, London E13 0DN; Valetta Grove building, 200 Plaistow Road, London E13 0FB, United Kingdom